Time Line of LIGO Events
 
1970
Feasibility Studies and early work on laser interferometer gravitational- wave detector
     
1979
National Science Foundation (NSF) funds Caltech and MIT for laser interferometer R&D
     
1989
December
Construction proposal for LIGO submitted to the NSF
     
1990
May
National Science Board approves LIGO construction proposal
     
1991
March
LIGO project receives 19 site proposals from 17 states
 
LIGO 40-meter interferometer operated with LIGO displacement sensitivity
 
Fall
Congress approves first year funding for LIGO
     
1992
February
NSF selects LIGO sites: in Hanford, Washington, and Livingston, Louisiana.
 
May
LIGO Cooperative Agreement signed by NSF and Caltech
     
1993
Spring
Congress funds LIGO for the second year of construction
 
Summer
NSF review panel endorses technical status of LIGO
 
Start of LIGO vacuum system engineering design
 
August
Contract for beam tube design signed
     
1994
Spring
Congress funds LIGO for the third year of construction
 
July
Groundbreaking at Hanford site
 
Summer
Congress funds construction in FY95
 
October
Louisiana site land transfer and leasing agreement executed
 
Fall
NSF approves new cost/schedule management review
     
1995
July
Groundbreaking at Livingston site
 
Fall
Congress approves FY96 funding for LIGO construction
 
Fall
Contract for vacuum equipment and for vacuum beam tube fabrication signed
     
1996
Summer
Contracts for construction of buildings and concrete slab at Hanford signed
 
September
Contract for construction of beam tube enclosures at Hanford signed
 
October
Installation of vacuum beam tubes begins at Hanford site
 
December
Raw glass for mirrors received by LIGO
 
Contract for construction of buildings, concrete slab, and beam tube enclosures at Livingston site signed
     
1997
June
First polished glass received by LIGO
 
July
LIGO prototype demonstrated “splitting a fringe” at LIGO sensitivity goal
 
August
Buildings at Hanford accepted and occupied by Caltech
 
First of four 10-Watt lasers received by LIGO for testing
 
October
Installation of vacuum beam tubes begins at Livingston site
 
December
LIGO receives final shipment of raw glass
     
1998 February All vacuum beam tube modules at Hanford accepted
  May First completed mirrors arrive at LIGO
  September 40-Meter interferometer operated with LIGO optical configuration
   
First 10-Watt stabilized laser installed at Hanford
   
Installation of seismic isolation system begins at Hanford
  October
Buildings at Livingston accepted and occupied by Caltech
    First beam tube module at Hanford is baked to remove excess water and other chemicals
  November
Vacuum system at Hanford accepted by Caltech
    All vacuum beam tube modules at Livingston accepted by Caltech
  December
First fully characterized mirror arrives at Hanford
     
1999 January
Vacuum system at Livingston accepted by Caltech
 
February
Installation of seismic isolation system begins at Livingston
 
April
Polishing of mirrors complete
  May
All beam tube modules at Hanford are baked
 
June
Coating of mirrors complete
  September
First vacuum beam tube module at Livingston completes bake
  November
LIGO Inauguration Ceremony
     
2000
May
Completed installation of interferometer components for Hanford 2-km interferometer
 
June
Completed bake of the beam tube(s) at Livingston
 
October
Achieved “first lock” on Hanford 2-km interferometer in power-cycled configuration
     
2001
February
Earthquake in Washington State disrupts commissioning
 
December
E7 Engineering Run, first coincident operation of all three LIGO interferometers plus GEO600 interferometer in Germany and LSU bar detector
     
2002
August
First scientific operation of all three interferometers in S1 run operating with GEO600 and TAMA300 (Japan) interferometers
 
Fall
Continued commissioning leading to improved sensitivity
     
2003
Feb-April
Second science run (S2) operating with TAMA300 interferometer
  Summer Continued commissioning leading to improved sensitivity
  Nov-Dec Third science run (S3) operating with GEO600 and TAMA300 interferometer
     
2004 Mar - June Installation of active anti-seismic system at Livingston
    Upper limits papers using S1 data published in Physical Review
     
2005 November Begin year long data run at design sensitivity ("S5")
     
2005-   Improved upper limits uing data from S2-S4 published
2006 November Open LIGO Science Education Center in Livingston